Relocation of Testing Laboratories for BAXI

Instalaciones
11/6/2026

BAXI, a leading company in climate control and heating solutions, continues to invest in the optimisation of its production processes. In this context, Grupo Savia has participated in a key project involving the relocation of its testing laboratories and production equipment, ensuring operational continuity and maximum efficiency throughout every stage of the process.

The project involved the disconnection, dismantling, relocation, and installation of services at the destination site to support production operations, including all associated equipment and services.

Disconnection and Dismantling of Equipment up to the Flange Connection Point

A controlled disconnection of all services (electrical, mechanical, and process-related) is carried out, ensuring the proper identification, labelling, and traceability of each element. Dismantling is performed up to the flange connection point, preserving the integrity of the connections and facilitating their subsequent reinstallation without issues.

 

Preparation of Equipment for Safe Transportation

The equipment is prepared using specific protection measures according to its type (technical packaging, securing systems, and protection of sensitive components), ensuring structural stability and preventing damage during handling and transportation.

 

Use of Specialised Lifting and Auxiliary Transport Equipment

Lifting equipment adapted to each asset (cranes, platforms, and lifting systems) and specialised transport solutions are used, enabling safe manoeuvres in active industrial environments while optimising execution times.

 

Relocation to the New Designated Location

The equipment is positioned according to the previously defined layout, ensuring correct alignment, levelling, and operational clearances. This phase is key to ensuring the proper integration of the production line into its new operating environment.

 

Interconnection of All Elements

The complete reconnection of all services and systems (electrical, pneumatic, hydraulic, and control systems) is carried out, ensuring the functional continuity of the facilities while complying with the original technical specifications.

 

Integrated Commissioning of the Installation

Functional testing, operational verifications, and final adjustments are carried out to ensure that the production line operates in a coordinated, safe manner and in accordance with the required production parameters.

The operations were carried out within the production areas, both at the original location and at the final destination, ensuring proper planning of all movements and the safe use of internal routes.

Collaborating with companies such as BAXI, committed to continuous improvement and industrial excellence, reinforces our approach to delivering reliable, results-oriented solutions.